The Mt. Vernon City Council and the Mt. Vernon Parks and Recreation Board met for a Joint Workshop Meeting on Wednesday, October 26, 2011, at 5:00 p.m. in the Rolland W. Lewis Community Building, 800 S. 27th Street, Mt. Vernon, Illinois.

 

City Clerk Jerilee Hopkins called the Joint Workshop Meeting to order. 

 

Roll call showed present: Councilman Dennis McEnaney, Councilman Todd Piper, Councilman David Wood, and Mayor Mary Jane Chesley.   Councilman Ron Lash was absent.  Also present:  City Manager Ron Neibert, Parks and Recreation Department Director George Bryant, Parks and Recreation Department Coordinator Wes Plummer, Park Board Member Bernie Dickneite, Park Board Member Trinda Heitmeyer, Park Board Member Jerry Harpole, and Park Board Member Donte Moore.  Roger Greenwalt of FGM Architects and Scott Hester of Counsilman-Hunsaker also attended.

 

Scott Hester of Counsilman-Hunsaker made a presentation about the process of developing an Aquatics Facility Master Plan that would evaluate the options for the future of aquatics in the Mt. Vernon community.  The team of FGM Architects and Counsilman-Hunsaker has been commissioned by the City to assist the community in the preparation of the master plan. 

 

Mr. Hester commented that Counsilman-Hunsaker is already doing several things behind the scenes as far as looking at the Mt. Vernon market, including demographics, income levels, age group distribution, community growth, and other area providers. 

 

In the feasibility study, they will identify a series of concepts for consideration based on the programmatic input collected from all the stakeholders’ groups involved. Collectively, with the Steering Committee, George Bryant, Wes Plummer, FGM, and Counsilman-Hunsaker, will define the level of options to be analyzed.  At that point a determination will be made as to the capital costs, operational expenses, as well as the revenue potential. 

 

 

The following stakeholders have met with Counsilman-Hunsaker and FGM Architects: hospitals and health care providers, local school administration, swim team, City government, the Parks and Recreation Board, and the Steering Committee.

 

Counsilman-Hunsaker will look at various locations throughout the community to be considered for the aquatic project.  They will also review the current location of the City pool to determine if it’s the best site for the new project.  Perhaps other public or private entities may decide to invest in the project which will also drive the location process.  Counsilman-Hunsaker will compare their findings to national averages and other facilities comparable across the country to determine acceptable levels of user fees and what the public is willing to pay for this facility.

 

The present facility was built in 1968.  Considering the age and wear and tear on the facility, the City has done a very good job of maintaining the pool.  Unfortunately, there are leaky pipes, ADA accessibility challenges, and other functional problems and physical repairs required to bring it up to code.  It is possible that these repairs can amount to several hundred thousand dollars to one million dollars.  In essence, by repairing the old pool we are creating a brand new 1968 pool.  Counsilman-Hunsaker will assess these factors in the feasibility report. 

 

On the recreation value side of the existing pool, a renovation can include a slight reconfiguration of the pool, maybe a zero depth entry, and/or bring in water slides, etc. There will be site constraints; the present bathhouse is sized to accommodate the current pool capacity and once you add all the other water and fixtures (sinks, showers, and toilets), the renovation or functional improvements are limited based upon the support space.  Ultimately, when dealing with a facility of this age, you’re faced with replacing the entire facility, including the pool and all support space around it.   

 

Discussion was held regarding the community’s expectations as to whether the project is opportunity driven or economic driven.  On a new seasonal outdoor facility, Mr. Hester estimates that one should be able to meet or exceed the cost to operate the facility.  In fact, one may be able to generate a slight amount of revenue.  An indoor facility becomes more challenging because it’s operating all year around, it must be heated and cooled, and a larger number of staff is required for daily operation.  It is more difficult to recover the operating expenses.  Mr. Hester is not speaking against the indoor facility, but about the recapture rate.  In other words, 100 percent of revenues would be equivalent to the total cost of expenses.  That means you’re at 100 percent recapture rate.  If you’re at 110 percent, then you are 10 percent beyond that.  If you’re at 80 percent, then you’re only recapturing 80 percent of your expenses.  On an indoor recreation center, common recapture rates are at the 69 percent range.  On an outdoor aquatics facility, you will be at a 95 to 110 percent recapture rate. City Manager Ron Neibert confirmed that the recapture rate is based solely on operational costs with no capital costs included.

 

         

 

There are four different user groups:

1)    Competitive — includes swimming, diving, water polo and synchronized swimming with specific depth and lane requirements;

2)    Recreation and leisure;

3)    Instruction and lesson programs; and

4)    Wellness and therapy programs.

       

The local swim team meets at the City pool only during the months of June and July. They are requesting a 25 meter pool with six or eight lanes.  A 50 meter pool is too large for the needs in our community.  There is always the opportunity to include multiple uses in the competitive pool such as rock climbing, zip lines, water basketball, and water volleyball and floatable structures. 

 

Recreational users include all ages and usually shallow water depth from zero entry to three and one-half to four feet of water depth.  This area of the pool is all about activity, including water slides and interactive play structures similar to the Salem, Illinois facility.  Instruction and lesson programs include learn to swim classes, lifeguard training, scuba training, and any sort of instructional activity.  Open water areas at various depths will be needed.

 

Wellness and therapy is the fastest growing group in aquatic facilities.  Water aerobics, senior classes, rehabilitation programs are some of the various activities that can be offered.  Water temperature is important for this category and probably will require a dedicated, stand-alone pool so that the water can be heated.  Recreational and competitive swimmers like cooler water.  If it’s a seasonal pool, heating the water won’t be an option.  Most pools are not heated in this part of the country. 

 

Mr. Hester noted that he is originally from Salem and Counsilman-Hunsaker performed the work on the pool in Salem.  They started their pool project in November 2007.  They also met with various stakeholders in the community as well as the Steering Committee. Counsilman-Hunsaker drafted a feasibility study for the City of Salem outlining three different options ranging in cost.  Salem chose to focus on an outdoor pool with an indoor therapy pool component.  They constructed an eight lane 25 meter pool and one meter and three meter diving boards.  Salem realized a large indoor pool similar to Centralia’s wasn’t achievable for them because of the cost factor and the close proximity of Salem to Centralia’s indoor pool.  In November 2008, the voters in Salem passed the referendum and the City Council adopted a half-cent sales tax increase.  By calculating how much they could generate from the outdoor pool, they decided the best chance for success was to replace the existing outdoor pool and make it very, very nice. The indoor therapy pool was not feasible due to the added cost of $1.5 million. 

 

They applied for, and received, a $400,000 OSLAD grant from the State of Illinois’ Department of Natural Resources.  In the fall of 2008, Counsilman-Hunsaker completed the engineering drawings and submitted them to the Department of Health in February 2009 for their review.  In May 2009, they released the contract for bidding and by June 2009 they had selected a construction contractor.  They closed the old pool down two weeks early in August 2009 in order to begin construction.  The new facility was opened in May 2010.  Mr. Hester described the two and one-half year timeline followed by Salem in order to show the lengthy process needed to finish a new facility.       

 

If the City of Mt. Vernon followed a similar timeline, a new facility would be ready for business in May 2014.  He noted that it takes four to six months to complete the design work for an outdoor pool, and six to eight months to complete the design work on an indoor facility.  Additionally, to complete the construction of an outdoor pool would be at least nine months and probably one and one-half years for an indoor facility. 

 

Mr. Hester presented a before and after pictorial of Salem’s Family Aquatic Center.  The total cost of their facility was $4 million, including demolition of the old facility. Previously, the City of Salem subsidized the pool operations in the amount of $30,000.00 to $40,000.00 a year.  That is about double the amount the City of Mt. Vernon subsidizes the park pool.  The first year Salem was in operation they generated about $30,000.00 in positive revenue.  More revenue is generated by the concession stand.  

 

Counsilman-Hunsaker will present a final study report which will be between 75-100 pages including current trends in the industry, analysis of other area providers, and capital outlay for each option with operational expenses, suggested user fees and revenues.  

 

Council Member David Wood left the meeting at 6:00 p.m.

 

Mr. Hester noted that occasionally a city will partner with another city school or YMCA on the capital costs and will split the costs on a percentage basis by how much the school or outside agency is utilizing the facility. It’s possible for the city to fund the construction and the school to fund the operations.  There are situations in which the city funds the project, and the YMCA is the operator of the facility.  In addition, villages, counties, cities and other public or private entities may form partnerships to provide an aquatic facility in their community.  Generally, these partnerships are formed for large indoor facilities.  He advised that he will give the City information regarding three different municipalities in Pennsylvania that formed a recreation cooperative or district.

 

The meeting adjourned at 6:25 p.m.