Mount Vernon
Comprehensive Planning Process
August
18th, 2008 - Steering Committee Meeting.
Each
subcommittee will present a status report of their
activities.
The
sub-committees should be gaining a baseline
understanding of the operational status of the city in
their specific areas of investigation. This
baseline understanding should form the catalyst to
initiate a dispositional dialogue regarding their
feelings of the City's present operational status
within the defined area of the sub-committee.
The dialogue and investigation should begin to move
the sub-committees toward the identification of
targets for change and improvement. During
September and October it is suggested that the
committees begin the identification and investigation
of some tentative strategic initiatives for the city.
DMi will
complete the comprehensive review of the City's
operations in the areas being investigated by each of
the subcommittees. They will provide the
baseline data to each of the sub-committees in the
form of a "Fact Book" document.
DMi will
continue to support each sub-committee with all their
data acquisition needs.
DMi will
continue to meet with each of the sub-committees and
to document the sub-committee's progress in
investigating their specific area of the Comprehensive
Plan.
DMi will provide
the Mayor and the Steering Committee Chair with
written monthly updates regarding the progression of
the City's Comprehensive Plan.
October
30th, 2008 - Steering Committee Meeting.
Each
subcommittee will present a status report of their
activities.
The
sub-committees will be asked to prepare a presentation
including a listing of tentative strategic initiatives
that have been reviewed and investigated by the
sub-committee's membership. Movement toward a
prioritization of the Strategic Initiatives should
begin at this point. At the December Steering
Committee Meeting ... sub-committees will be asked to
provide a prioritized listing and description of
initiatives that have been investigated. The
listings will be cross referenced with each of the
sub-committees to identify areas of replication,
conflict and possible synergistic leveraging.
DMi will present
a report to the Steering Committee regarding their
work with the sub-committees and a summary report
regarding their perception of the status of the
progress of the Comprehensive Plan.
DMi will
continue to meet with each of the sub-committees and
to document the sub-committee's progress in
investigating their specific area of the Comprehensive
Plan.
DMi will
continue to support each sub-committee with all their
data acquisition needs.
DMi will review
the status reports of each sub-committee and examine
the lists of strategic initiatives being reviewed.
An analysis of the work of each sub-committee will be
conducted by DMi. They will screen the
sub-committee reports for the purpose of determining
the relationship of the initiatives being reviewed and
discussed from one sub-committee to another. The
purpose of the analysis is to assure the systemic
connection of the work of the sub-committees.
DMi will provide a report of their analysis to the
Mayor and Chair of the Steering Committee at their
November 7th meeting.
December
11th, 2008 - Steering Committee Meeting.
Subcommittees
should be prepared to provide a list of prioritized
initiatives that have been investigated by their
subcommittee's membership. The prioritized
initiatives should be supported with a brief
description of the specific nature of the initiative
and how it relates to the sub-committee's area of
investigation. The subcommittees should begin to
narrow down the listing of strategic initiatives that
will form the foundation for their final report.
A draft of the subcommittee's report will be presented
at the January Steering Committee meeting.
DMi will present
a report to the Steering Committee regarding their
work with the sub-committees and a summary report
regarding their perception of the status of the
progress of the Comprehensive Plan.
DMi will begin
the development of the format for the draft versions
of the City's Comprehensive Plan document.
DMi will
continue to support each sub-committee with all their
data acquisition needs.
DMi will provide
the Mayor and the Chair of the Steering Committee with
a report outlining the procedures to be followed in
bringing the report data from each sub-committee
together for the purpose of compiling the draft plan
document.
DMi will
continue to meet with each of the sub-committees and
to document the sub-committee's progress in
investigating their specific area of the Comprehensive
Plan.
February,
2008 -
Steering Committee Meeting.
The
sub-committees will present their draft report
summarizing their work. The draft should include
information regarding their engaged activities, the
strategic initiatives that were investigated, and a
summation that will include their findings followed
with a formal recommendation of the Strategic
Initiatives that should be considered and pursued.
The information received from each sub-committee will
be used to formulate a draft report to the City
Council for review. The sub-committees should be
prepared to present their final report at the February
3" Steering Committee meeting.
DMi will present
a report to the Steering Committee regarding their
work with the sub-committees and a summary report
regarding their perception of the status of the
progress of the Comprehensive Plan.
DMi will
continue to meet with each of the sub-committees and
to document the sub-committee's progress in
investigating their specific area of the Comprehensive
Plan.
DMi will provide
the Mayor and the Chair of the Steering Committee with
a draft version of the Comprehensive Plan.
March/April, 2008 - Steering Committee Meeting.
The
sub-committees will present their final report
summarizing their work. The final report should
include information regarding their engaged
activities, the strategic initiatives that were
investigated, and a summation that will include their
findings followed with a formal recommendation of the
Strategic Initiatives that should be considered and
pursued. Sub-committee chairpersons will be
asked to assist with compiling all sub-committee
reports into the draft Comprehensive Plan that will be
presented to the City for review for the City.
DMi will compile
all the reports including all final additions or
modification into the preliminary presentation copy of
the City's Comprehensive Plan. DMi will provide
a status report to the Mayor and Chair of the Steering
Committee regarding the progress in the development of
the final draft of the "Plan." The presentation
copy will be presented by DMi at the Steering
Committee's February 3'' meeting.
DMi will review
information received from the report review sessions
and use this information to prepare the Comprehensive
Plan for presentation to the City Council for review
at its February meeting.
May, 2008 -
Comprehensive Plan Adoption.
The
sub-committees will be asked to be present at the City
Council Meeting for the purpose of presenting the
City's Comprehensive Plan for adoption.
DMi will prepare
the City Comprehensive Plan for presentation at the
March meeting of the City Council for adoption.
DMi will assist in the presentation to the Council.