The City of Mt. Vernon invests a significant amount of funding every year into projects to maintain and repair miles of city roads. The Streets Division of the Public Works Department performs maintenance to streets and alleys, including minor patches and potholes. Contractors are often hired for larger or more specialized projects. 

While the city and its contractors do their best to keep roads safe and traffic moving, backups can still occur. Please plan ahead and consider using alternate routes. Below is a list of scheduled projects and temporary road closures.

Please note that this may not be a complete list of road projects as emergency repairs may come up.

Active Projects

Project Details: Extending 44th Street from Mateer to Ilberry and Heritage

Start Date: 3/7/2024

Estimated Completion Date: Summer 2024

Location: South 44th Street

Estimated Project Cost: $3,679,714.27

Contractor: Guinzy Construction

3/4/24 - Bid awarded 
2/28/24 - Bid opening
1/2/24 - City Council approved bidding of the project

Dirt, trees, and sky
Clearing for the road

Project Details: This project is part of the city's annual street maintenance program. The below map shows which streets are on the list for this year.

Anticipated Start Date: May 1, 2025

Estimated Completion Date: October 1, 2025

Location: Various streets throughout the city

Estimated Project Cost: $325,000

Contractor: Out to bid

Road map of city
Street Maintenance Program Planned Streets

Project Details: This project consists of asphalt milling and overlaying on various streets throughout the city.

Anticipated Start Date: Spring 2025

Estimated Completion Date: Fall 2025

Location: Various streets throughout the city

Estimated Project Cost: $325,000

Contractor: Out to bid

Road list with maps

Project Details: This project is part of the city's annual maintenance program. Every year various parking lots are resealed and striped throughout the city.

Anticipated Start Date: Spring 2025

Estimated Completion Date: Fall 2025

Location: Various throughout the city

Estimated Project Cost: $

Contractor: Out to bid

 

Street map of city
Map of project locations

 

 

Project Details: Every year the Public Works department selects places throughout the city that need remarked. This year 104,288 lineal feet of 4' pavement marks are to be repainted in the city.

Anticipated Start Date: Spring 2025

Estimated Completion Date: Fall 2025

Location: Various locations throughout the city

Estimated Project Cost: $

Contractor: Out to bid

 

Road map of city
Pavement Marking Map

 

Project Details: Approximately 1 block of curb will be removed and new curb, parking lanes, and sidewalk will be installed.

Anticipated Start Date: Spring 2025

Estimated Completion Date: Fall 2025

Location: Harrison Street, between the alley and 9th Street

Estimated Project Cost: $

Contractor: Out to bid

 

Street map
Map of streetscape project

 

 

Completed Projects

Project Details: Re-striping of half of the pavement markings citywide.

Start Date: 7/13/2023

Completion Date: 8/30/2023

Location: Citywide

Estimated Project Cost: $19,537

Contractor: Varsity Striping

Project Details: Re-striping of half of the pavement markings citywide.

Estimated Start Date: Summer 2024

Estimated Completion Date: Fall 2024

Location: Citywide

Estimated Project Cost: $13,408.80

Contractor: Varsity Striping and Construction Co.

6/17/2024 - Council awarded bid
5/20/2024 - Council approved bidding.

Map of streets in Mt. Vernon
City Wide Pavement Marking Project Map

 

Project Details: Asphalt overlay on roads throughout the city.

Start Date: 7/7/2023

Completion Date: 10/4/2023

Location: Citywide

Project Cost: $585,507

Contractor: E.T. Simmonds

Project Details: The city overlays asphalt on roads throughout the city.

Start Date: 7/7/2023

Estimated Completion Date: Spring 2024

Location: Citywide

Estimated Project Cost: $360,000

Contractor: In House

2023 Annual Road Maintenance Program Map
2023 Annual Road Maintenance Program Map

Contractor: E.T. Simonds, Jax Asphalt, Inhouse

Project Details: The city overlays asphalt on roads throughout the city.

Estimated Start Date: Summer 2024

Estimated Completion Date: Fall 2024

Location: Citywide

Estimated Project Cost: $674,395.00

Contractor: In House

6/17/24 - Bids for materials were awarded
5/6/2024 - Council approved project

Project Details: Repairing faulty sections of Davidson Avenue with concrete patches.

Estimated Start Date: Summer 2024

Estimated Completion Date: Fall 2024

Location: Davidson Avenue, on the Northside of Route 15, by the Pilot Truck Stop

Estimated Project Cost: $152,449.29

Contractor: Shores Builders

6/3/2024 - Shores Builders awarded bid
5/6/2024 - Council approved bidding

 

Davidson Avenue Road Patch Project Map

 

Project Details: New asphalt added to the parking lot

Start Date: 10/1/2023

Completion Date: 11/6/2023

Location: Optimist Park

Project Cost: $2,670

Contractor: In House

Project Details: Reseal parking lots 

Start Date: 6/23/2023

Completion Date: 8/30/2023

Location: City Hall, Post Office

Project Cost: $15,038.00

Contractor: Jax Asphalt

Project Details: Asphalt overlay parking lots 

Start Date: 8/25/2023

Completion Date: 10/1/2023

Location: Veterans Park Northeast Parking Lot

Project Cost: $92,440

Contractor: Jax Asphalt